Maintenance Window Schedule:
March 21, 2010 starting at 00:01-02:00 CST (06:01-08:00 GMT)
Why are we conducting this maintenance?
In order to ensure ideal conditions exist to promote maximum uptime, Rackspace monitors power utilization, cooling efficiency, and port density in all of our data center facilities. In order to complete the Power Factor Upgrade in our DFW data center, power cables from one circuit to another must be migrated. During a previous maintenance on the UPS clusters, technicians upgraded the fans and power supplies with more efficient equipment. These new fans and power supplies draw less power, which in turn releases more capacity to be available on the UPS cluster. In order for the system to recognize this additional power, firmware was upgraded on each UPS cluster. The final step of this maintenance is to migrate the power cables from one circuit to another.
If you have any further questions, please contact a member of our support team by visiting us in live-chat or by calling 1.877.934.0407 or INTL +1.210.581.0407.